TM 5-5420-234-14&P
2-16. HIGH-BANK BRIDGE BAY LAUNCH (continued).
(47) Put transmission in forward, and release parking brake.
(48) Move Transporter forward sufficiently for another bridge bay to be unloaded next to edge of high
bank.
NOTE
If this is the last bridge bay to be launched, go to Step 50. Otherwise, go to Step
49.
15
(49) Repeat Steps 23 through 48.
(50) Position HIGH IDLE switch (15)
to ON.
18
16
19
(51) Position MAIN FRAME switch (18) to UNLOAD and release when main frame is fully extended.
(52) Position HOOK ARM switch (16) to UNLOAD and release when winch cable hook is about 5 feet (1.5
m) above the ground.
(53) Position HIGH IDLE switch (15) to OFF.
(54) Remove lifting sling from snatch block (22) hook.
(55) Return sling to stowage.
(56) Remove snatch block (22) and extension assembly (21) from winch frame.
(a)
Remove snatch block (22) from winch
cable (20).
21
(b)
Remove winch cable (20) from extension
assembly (21).
(c)
Remove extension assembly (21) from winch
frame.
(d)
Return snatch block (22) and extension assembly
20
(21) to stowage.
22
(57) Position WINCH switch (19) to IN.
2-92