I 15-14. 2500 GALLON TANK REMOVAL/INSTALLATION (M978) (CONT). [
(16) Install two nuts (31 and 32) and tubes (33 and 34) on elbows (35 and 36).
c. Follow-on Maintenance.
(1) Install tank vent (para 15-15).
(2) Install V13 vent valve (TM 9-2320-279-20).
(3) Install V10 bottom load valve (TM 9-2320-279-20).
(4) Install V19 jet level sensor (TM 9-2320-279-20).
(5) Install V1 emergency valve cable (TM 9-2320-279-20).
(6) Install emergency shut-off cable (TM 9-2320-279-20).
(7) Install primary pump to flow limiting valve piping (TM 9-2320-279-20).
(8) Install primary pump (TM 9-2320-279-20).
(9) Install V3 suction line valve to primary pump piping (TM 9-2320-279-20).
(10) Install V3 suction line valve (TM 9-2320-279-20).
(11) Install line strainer piping (TM 9-2320-279-20).
(12) Install emergency valve outlet piping (TM 9-2320-279-20).
(13) Install stowage tube (TM 9-2320-279-20).
(14) Install side reflectors (TM 9-2320-279-20).
(15) Install side clearance light wiring (TM 9-2320-279-20).
(16) Install side clearance lights (TM 9-2320-279-20).
(17) Install fuel level sensor (TM 9-2320-279-20).
(18) Install vent rollover guards (TM 9-2320-279-20).
(19) Install dipstick tube (TM 9-2320-279-20).
(20) Install stowage box B (TM 9-2320-279-20).
(21) Install center mud flaps (TM 9-2320-279-20).
(22) Install ladder (TM 9-2320-279-10).
(23) Prepare tanker for operation (TM 9-2320-279-10).
(24) Fill tank with fuel by performing bottom loading (TM 9-2320-279-10).
(25) Recirculate fuel (TM 9-2320-279-10).
(26) Inspect pump module and piping connection for leaks and proper operation.
END OF TASK