T M 9 - 2 3 2 0 - 2 7 9 - 3 4 - 1
Electrical System Maintenance Instructions (Cont)
(2) Remove two nuts (4), lockwashers (5), screws (6), and bracket (7).
N O T E
All four overload switches are removed the same way.
Iag and mark overload switches before removing.
(3) Remove nut (8) and overload switch (9) from mounting bracket (10).
N O T E
The three overload switches are removed the same way.
Remove clamp, wire ties and clips as necessary.
Iag and mark overload switches before removing.
(4) Remove four screws (11) and mounting flange (12) from mast (13).
(5) Remove overload switch (14) from mounting flange (12).
(6) Remove two screws (15), lockwashers (16), and sensor plate (17).
6-70.1