TM 9-2320-279-20-2
Winches, Cranes, and Power Takeoff (PTO) Maintenance Instructions (Cont)
(5) Install two chains (6) on quick pins (7).
(6) Install two chains (6) on studs (8) with two washers (9) and nuts (10).
d. Follow-on Maintenance. Install outrigger pads (TM 9-2320-279-10).
END OF TASK
17-33. OUTRIGGER BEAM ASSEMBLY COVER REMOVAL/INSTALLATION.
This task covers:
a. Removal
c. Follow-on Maintenance
b. Installation
INITIAL SETUP
Models
References
M984E1
None
Test Equipment
Equipment Condition
None
TM or Para
Condition Description
Special Tools
TM 9-2320-279-10 Shut off engine.
None
Special Environmental Conditions
Supplies
None
None
General Safety Instructions
Personnel Required
None
MOS 63S, Heavy wheel vehicle mechanic
17-159