TM 9-2320-279-20-2
Brake and Air System Maintenance Instructions (Cont)
(5)
Install No. 4 air manifold (5) on
bulkhead (12) with four screws (13) and
lockwashers (14).
(6)
Connect seven air lines (15), two air
lines (16), and two air lines (17) on
No. 4 air manifold (5).
(7)
Connect eight air lines (18), two
air lines (19), and air line (20) to
No. 4 air manifold (5).
(8)
Connect two electrical leads (21)
to pressure switch (4) with
washers (22) and nuts (23).
NOTE
Install plastic cable ties as needed to
secure air lines.
c.
Follow-on Maintenance.
(1)
Connect batteries (para 7-91).
(2)
Start engine and build up air
pressure (TM 9-2320-279-10).
(3)
Check air connections for leaks.
(4)
Shut off engine
(TM 9-2320-279-10).
Change 2
11-107